Strategic Outline Case for Station Approach (less exempt appendices)
July 18, 2023 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
... the Cabinet of Winchester approved the Strategic Outline Case for the Station Approach project, agreeing to progress the project by developing a concept masterplan and delegating authority for its procurement, as well as releasing £295,000 from the Regeneration Reserve to fund stage 2.
Full council record
Decision
- That feedback provided by the Scrutiny Committee at its meeting on 3rd July 2023 be noted.
- That the Strategic Outline Case for Station Approach be considered and the recommended approach to progress the project as outlined in Option 3 of section 13.3 in report CAB3413 be agreed.
- That authority be delegated to the Strategic Director with responsibility for the Station Approach project, in consultation with the Leader and Cabinet Member for Asset Management to finalise the brief to procure the concept masterplan as outlined in points 4 and 5 below.
- That the procurement and subsequent award and entering into a contract of a multi-disciplinary team to produce a concept masterplan for Station Approach be agreed as outlined in sections 3.2 and 14 of the report.
- That an evaluation model of 70% Quality / 30% Cost for the procurement of a multi-disciplinary team to produce a concept masterplan for Station Approach be agreed as stated in section 3.2 of the report.
- That the release of £295,000 from the Regeneration Reserve to fund stage 2 of this project be approved, as set out in section 12.5.3 of the report.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 18 Jul 2023 |
| Effective from | 27 Jul 2023 |
| Subject to call-in | Yes |