1.      
That up to £3.25m of HRA capital expenditure
in 2024/25 be approved, using the existing retrofit budget, for the
retrofit of 21 Swedish cottages and up to 150 loft insulation
top-ups and associated works.
 
2.      
That authority be delegated to the Strategic
Director - Services to be authorised to award and enter into a JCT
Standard Building Contract to retrofit 21 Swedish Cottages and
improve the loft insulation in up to 500 properties with Synergize
Ltd.
 
3.      
The Strategic Director - Services to be authorised
to negotiate and agree contractual terms with the contract
appointment.
 
4.      
That authority be delegated to the Service Lead:
Legal to prepare and enter into all relevant agreements, negotiate
the contractual agreements, and see them to completion to enable
the successful delivery of the Retrofit Works.