Liscard Levelling Up Fund 3 Programme
March 12, 2025 Economy Regeneration & Housing Committee (Committee) Key decision Approved View on council websiteFull council record
Purpose
To provide an update to Committee on the
Liscard Levelling Up Fund 3 Programme
Decision
Resolved –
That
1.
Policy and Resources Committee be requested to recommend
that:
a. The Liscard Levelling Up Fund programme be
progressed as a standalone programme and not incorporated into the
remit of the Simplification Pathfinder Pilot Board; and
b. The Director of Regeneration and Place be
authorised to:
i.
enter into a Memorandum of Understanding regarding the Liscard
Levelling Up Fund allocation, in consultation with the Director of
Law and Corporate Services;
ii.
progress delivery of the Liscard Levelling Up Fund Programme, in
line with the Grant funding provision and the Approved Project as
described under paragraph 3.5 of this report; and
iii.
implement any necessary change control process in consultation
with Economy, Regeneration & Housing Committee’s Chair
and group spokespersons.
2.
The update regarding the Town Centre Regeneration and Public
Realm Interventions and the Community Hub be noted.
Related Meeting
, Economy Regeneration & Housing Committee - Wednesday, 12th March 2025 6.00 p.m. on March 12, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 12 Mar 2025 |
| Subject to call-in | Yes |