The Executive decided to note the update on the Barkham Solar Farm project and that the Deputy Chief Executive is progressing the project in accordance with delegated authority. The Executive noted the current grid connection position, implications of delay, and residual risks associated with proceeding ahead of full contractual certainty.
Full council record
Purpose
To update the Executive on the Barkham Solar Farm project and agree next steps in the delivery of the project.
Decision
RESOLVED that the Executive noted:
- the update on the Barkham Solar Farm project, including the current grid connection position, programme status and implications of further delay and residual risks; and
- that the Deputy Chief Executive (S151 Officer), in consultation with the relevant Lead Member, is progressing the project in accordance with the delegated authority approved by Executive and Council in 2021.
Related Meeting
Executive - Thursday, 30 July 2026 - 7.00 pm on July 30, 2026
Supporting Documents
Details
| Reference | Call-ins0 |
| Outcome | Recommendations Approved |
| Decision date | 30 Jul 2026 |
| Effective from | 8 Aug 2026 |
| Expected date | 30 Jul 2026 |
| Originally due | 30 Jul 2026 |
| Lead officer | Sarah Morgan |
| Subject to call-in | Yes |