Capital Programme - Monitor 1 2026/27
September 9, 2026 Executive (Other) Unknown View on council websiteFull council record
Decision
Resolved: That the Executive:
i. In relation to the overall programme:
· Recommended to Council the adjustments resulting in a reduction in the 2026/27 budget of £5.008k as detailed in the report.
· Noted the 2026/27 revised budget of £107.982m as set out in paragraph 9 and Table 2.
· Noted the restated capital programme for 2026/27 – 2029/30 as set out in Annex 1.
Reason: To enable the effective management and monitoring of the Council’s capital programme.
ii. In relation to the investment at Burnholme:
· Noted the award of grant from the Football Foundation of £700k for a new 3G pitch at Burnholme delegating the Director of Finance to sign the grant agreements with Football Foundation and GLL for their contributions
· Agreed to adding the scheme to the capital programme with £150k CYC contribution from s106 / leisure sinking fund
· Approved the Council to enter into the framework partner agreements, construction contract and other contract documents required to deliver the contract.
· Accepted the risk that scheme cost overruns will need to be funded by the council.
Reason: To ensure that scheme funding can be accepted and the scheme delivery can progress in line with the Council’s Constitution and Financial Regulations.
Supporting Documents
Details
| Outcome | Decision Made |
| Decision date | 9 Sep 2026 |
| Effective from | 17 Sep 2026 |
| Subject to call-in | Yes |