September 7, 2026 at 4:30 pm View on council website Watch video of meeting Read transcript (Professional subscription required)Summary
Open Council Network is an independent organisation. We report on Norwich and are not the council. About us
Norwich City Council's Sustainable Development Panel noted the contents of the Greater Norwich Local Plan Authority Monitoring Report for 2024/25, which showed housing delivery above target overall but falling in Norwich, jobs growth well below target, and the city centre vacancy rate rising to 15.2% following the closure of Anglia Square for redevelopment. Members questioned whether the fall in retail frontage was a problem, how solar panels and heat pumps installed under permitted development would be counted, and whether quarterly update data could be published.
Housing delivery and the five-year land supply
The panel noted that the Greater Norwich Annual Monitoring Report 2024/2025 for April 2024 to March 2025, presented by Nyasha Dzwowa, a planning policy officer at Norwich City Council.
Across Broadland, Norwich and South Norfolk, 1,893 homes were delivered, slightly below the annual target of 1,990, but cumulative delivery remained ahead of schedule by more than 650 homes. Norwich delivered 180 homes, with 291 homes permitted in the year. Large permissions included 89 homes at Three Score, 67 at Mile Cross Depot and 48 at Norwich Community Hospital.
Officers attributed the fall in delivery and permissions to nutrient neutrality1, higher building costs, finance costs and the wider economic climate. The chair noted that figures for 2025/26 had now been compiled and would be published within a week or two, rather than waiting for the next annual report, and that the Greater Norwich five-year housing land supply2 was 4.85 years at 1 April 2025, down from 4.85 in the previous assessment described in the report. Without a five-year supply, the presumption in favour of sustainable development applies in decision-making, which officers said mattered more for Broadland and South Norfolk than for Norwich, where there are few greenfield sites. They said the best route back to a five-year supply was adoption of the new Greater Norwich Local Plan, which they hoped would be adopted in 2029.
Windfall housing3 accounted for 18.3% of delivery across Greater Norwich and 34% in Norwich, up on the previous year. Brownfield delivery4 fell to 12.4% across Greater Norwich, largely because of large greenfield urban extensions in Broadland and South Norfolk, while 83.9% of Norwich delivery was on brownfield land.
Affordable housing, jobs and employment land
Greater Norwich permitted 628 affordable homes, up from 476 the previous year, but still below target. Norwich permitted 115 affordable homes — 97 for social rent and 18 for affordable rent — and delivered 72. Officers said delivery fluctuated with the viability of individual sites.
Jobs growth was rated red. Greater Norwich added only 200 jobs in the year against a target of 2,222 a year. Norwich saw a slight increase, but employment in the city centre fell from 88,400 to 85,000 on the measure used, and office space continued to be lost. Officers described a longer-term redistribution of jobs from the city centre to out-of-town sites such as Broadland Business Park, driven by employers wanting modern, energy-efficient buildings, good road access and free car parking, and by the age and energy performance of older city offices.
Employment land delivery rose across Greater Norwich because of schemes in Broadland and South Norfolk, including at Broadland Gate and the John Innes Institute. There was no delivery on allocated strategic employment sites in Norwich in the year. B1a office space in Norwich fell by 432.62 sq m, much less than the previous year's loss linked to demolition of the former Marsh building, while B1c light industrial space gained 2,466.4 sq m, including at Twickenham Road.
City centre retail, vacancy and diversification
Councillor Lawes asked about the retail frontage in Norwich city centre, which the report rated red and which had fallen below minimum thresholds in four zones: PC02 Castle Mall, PR06 Timberhill/Red Lion Street, SR01 The Lanes West and SR03 St Benedict's Street.
Officers said this was not considered a worry. Changes to use classes5 since 2020 allow a shop to change to a café, restaurant or other service use without planning permission, so the council has less control than before, but the centre is diversifying. In response, one officer said: We wouldn't say it's a worry or a problem. It's just a nature of just how things are changing and that is just what the new use classes kind of promote just more flexibility.
The vacancy rate rose from 11.9% in the table to 15.2% in 2024/25, up from 13.3% cited in the Norwich summary, compared with a pre-pandemic figure of 5.5%. Officers attributed the rise mainly to the loss of units at Anglia Square, which is being redeveloped, and expected the rate to improve when new units at St Saviour's Yard were included. Footfall rose to 16,930,901. Officers said smaller units were re-let quickly, larger former department stores such as Debenhams and Wilko were more difficult, and Norwich compared favourably with many other town centres, with good daytime and evening footfall.
District and local centres had a vacancy rate of 8.6%, up from 7.8%. Most district centres remained above the 60% retail target, and most local centres above the 50% target, although many individual centres were below target.
Main town centre uses permitted inside defined centres fell to 762.35 sq m, compared with 14,679.3 sq m the previous year, because the previous year included Anglia Square. Permissions outside defined centres rose to 8,314.5 sq m, mainly for leisure at Whiffler Road, because no suitable premises of the right size were available in centres.
Carbon, air quality and sustainable design
Per capita carbon emissions continued to fall in all three districts to 2023, the latest year available, with Norwich lowest at 2.6 tonnes compared with 4.1 in Broadland and 5.2 in South Norfolk. Councillor Carlo criticised South Norfolk's higher emissions and the lag in central government data.
Air quality remained well below legal limits. At Lakenfields, nitrogen dioxide was unchanged at 8.5 micrograms per cubic metre, PM10 fell to 11.1 and PM2.5 to 7.2. At Castle Meadow 2, nitrogen dioxide fell to 22, but PM10 rose to 14.5 and PM2.5 to 8.6, partly attributed to polluted air imported from continental Europe and agricultural sources. Electric buses were credited with helping reduce nitrogen dioxide.
In Norwich, 32 applications included green design features such as water butts, permeable surfacing, soakaways and green roofs. Mile Cross Depot was to use Passivhaus principles6. No open space was lost contrary to policy.
Solar panels, heat pumps and permitted development
Councillor Oliver asked how the council would monitor solar panels and air-source heat pumps now that many domestic installations no longer need planning permission. In the year, 36 applications included renewable energy, with 1,357 solar panels and 21 air-source heat pumps permitted, including at John Lewis and Waitrose in Eaton.
Officers said the monitoring figure was not the full picture. Where permission is not required, the council has no automatic role and may not be informed. They said they relied on third-party sources, building control and industry bodies, and that the issue affected many monitoring indicators, not only renewable energy. Permitted development rights7 for rooftop solar and heat pumps meant, as one officer said, If it doesn't require planning permission, we don't have a role.
Development management decisions and other floorspace
Applications refused for loss of light and outlook totalled 61 dwellings, the highest on record, including 44 dwellings at 1-17 Westlegate. Nineteen dwellings were refused for falling below minimum space standards, including 15 at 5 Woolgate Court.
Community facilities gained 2,793 sq m, including padel tennis courts and clinical rooms at Magdalen Medical Practice. Education and training floorspace rose by 206,761.56 sq m because of the redevelopment of Hewett Academy. Evening economy floorspace was 719.75 sq m, down sharply on the previous year because that year included Anglia Square. City centre parking fell from 9,577 to 8,801 spaces, below the 10,000 maximum in policy, because of closures at Anglia Square, Magdalen Street, St Crispin's and Botolph Street, and losses at Rose Lane. Low-car housing8 accounted for 136 homes across five schemes.
Quarterly data and local government reorganisation
Councillor Carlo asked whether selected data, such as housing delivery and jobs, could be published quarterly online to give a more up-to-date picture and allow quicker corrective action. Officers said the 2024/25 report was published later than desirable, that work on 2025/26 was already under way with a hope of publication by the end of 2026 or early 2027, and that much monitoring data was collected only once a year and needed cross-checking across the three Greater Norwich authorities. They said they would investigate what could be published quarterly accurately, but warned there might not be much.
Councillor Carlo also said Norwich needed to become a unitary authority under local government reorganisation so it could plan strategically across its constrained boundary and stop employment shifting to the edge of the city. Officers responded that out-of-town relocation was a national trend, that the new Greater Norwich Local Plan would need to consider where new employment land should go and how to retain city centre jobs, and that regeneration and mixed-use development in the city were priorities, but that not all office space could or should be retained.
-
Nutrient neutrality is a requirement that new overnight accommodation, such as homes, must not add extra nutrients to the River Wensum Special Area of Conservation or the Broads Special Area of Conservation and Ramsar site. Permissions can only be granted if nutrient neutrality is demonstrated. ↩
-
A five-year housing land supply is the number of years of deliverable housing sites available to meet the housing requirement, including a buffer for choice and competition. If an authority cannot show five years, national policy gives more weight to housing proposals in decision-making. ↩
-
Windfall housing is housing delivered on sites that are not allocated in the local plan. ↩
-
Brownfield land is land that has previously been developed, including buildings and previously developed land in settlements. ↩
-
Use classes are categories in planning law that group land uses together. Since 2020, Class E combines shops, financial and professional services, restaurants and cafés, and offices, and changes within Class E, and from Class E to residential in some cases, can be made without planning permission. ↩
-
Passivhaus is a design standard that reduces energy use through high levels of insulation, airtightness and efficient ventilation and heating. ↩
-
Permitted development rights are rights to carry out certain development without first getting planning permission from the local authority. ↩
-
Low-car and car-free housing is housing approved with less than the normal amount of car parking, usually in sustainable locations with good public transport, walking and cycling links. ↩