Patrick Rodger

Council: Hackney

Committees: Cabinet Procurement and Insourcing Committee (Officer) Pensions Committee (Officer) (Council Staff)

Activity Timeline

Meetings Attended Note this may include planned future meetings.

37 meetings · Page 6 of 8

Committee

Hackney Procurement Board - Tuesday 10 December 2024 2.00 pm

This was not a public meeting, but a meeting in which officers were scheduled to make procurement key decisions. Following the meeting, notification of the decisions taken was to be published on the council website.

December 10, 2024
Committee POSTPONED

Hackney Procurement Board - Wednesday 13 November 2024 2.00 pm

This meeting has been postponed.

November 13, 2024
Pensions Committee POSTPONED

Pensions Committee - Wednesday 13 November 2024 6.30 pm

This meeting has been postponed.

November 13, 2024
Cabinet Procurement and Insourcing Committee

Cabinet Procurement and Insourcing Committee - Monday 4 November 2024 2.00 pm

This meeting was about awarding contracts for the provision of building works and refuse collection vehicles, and was scheduled to include a discussion about whether to bring the provision of some corporate security services in-house.

November 04, 2024
Committee

Hackney Procurement Board - Tuesday 8 October 2024 2.00 pm

The meeting included 10 reports. Six of these reports were about awarding new contracts for a variety of services, three were to approve extensions to existing contracts and one was about extending an existing apprenticeship training framework.

October 08, 2024

Decisions from Meetings

196 decisions · Page 1 of 40

F S650 Security Services Contract - Lots 1 & 2, Hackney Corporate Site Security, Vacant Buildings and Concierge Services

From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025

...to award framework agreements for four years to Supplier C for both Lot 1, providing security services, and Lot 2, providing concierge services, to the Council.

For Determination

F S624 Google Workspace Licences - Contract Award

From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025

...to ensure the continuity of essential services, they approved the award of a contract to Supplier C for the supply of Google Workspace licenses for an initial two-year term, with a one-year extension option.

For Determination

HCE S653 Kings Hall Leisure Centre (KHLC) Refurbishment Project - Enabling Works Design and Build contract award and Main Works Design and Build (D&B) Contract Award

From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025

...the committee approved the award of a JCT Design and Build Enabling Works contract and a JCT Design and Build Main Works contract to Morgan Sindall for the Kings Hall Leisure Centre Refurbishment Project, subject to Cabinet approval of the revised project budget.

For Determination

HCE S603 Parks Play Areas Refurbishments Phase 3: Design and Build Contract

From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025

...to award a JCT Design & Build contract for Phase 3 of the Play Area Refurbishment Programme to the most economically advantageous tenderer for £2,332,375, and to delegate authority to the Director Environment & Climate Change to finalize the contract.

For Determination

CE S640 Stoke Newington School - Creation of Additional Resourced Provision Assessment Centre and Media Suite Works

From: Cabinet Procurement and Insourcing Committee - Monday 1 December 2025 2.00 pm - December 01, 2025

...to appoint Contractor C as the Design and Build Contractor for the Stoke Newington School project, which includes an Additional Resourced Provision for 30 pupils and a media suite, starting from RIBA Stage 3+ onwards.

For Determination

Summary

Meetings Attended: 37

Average per Month: 1.9

Decisions Recorded: 196