Garioch Area Committee delegated the grant of full planning permission for a Battery Energy Storage System. This decision was made on 27/08/2024, subject to the approval of revised conditions by the Chair and Vice-Chair after officers review and amend wording.

Full council record

Purpose

Major application

Decision

Delegated grant subject to:-

  1. approval of revised conditions by the Chair and Vice-Chair following officers reviewing and amending wording of conditions 1 to 6 to ensure consistency of language and condition 10 to ensure the areas not planted due to underground pipelines and pylons are protected for the period of the development;
  2. remaining conditions as detailed in the report.

Supporting Documents

Community Council Comments.pdf
Presentation 2023-2310 Battery Storage at East of Kintore Substation.pdf