Provisional Outturn Report for the Financial Year 2023/24
June 18, 2024 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the Council's final revenue and capital outturn position for 2023/24, including addressing overspends in the General Fund, Housing Revenue Account, and Dedicated Schools Grant through reserve transfers and approving capital programme carry forwards.
Full council record
Purpose
The
Cabinet will be asked to approve the Council’s final revenue
and capital outturn position for 2023/24 and, if necessary, any
appropriate in-year budget adjustments.
Content
Cabinet resolved to:
(i) Note
that the General Fund provisional outturn position for 2023/24 was
£199.568m which, after a net transfer from reserves,
represented an overspend of £2.626m against the revised
budget of £194.460m, as detailed in section 2 of the
report;
(ii) Agree the
transfer of £2.626m from the General Reserve to achieve a
balanced outturn position for 2023/24;
(iii) Note the Housing
Revenue Account (HRA) provisional outturn position for 2023/24 was
an overspend of £6.060m which would be met from a reduced
contribution to the HRA Capital Reserve, as detailed in section 4
of the report;
(iv) Note that the
Dedicated Schools Grant (DSG) provisional outturn position for
2023/24 was an overspend of £2.118m which would be met from
the DSG Reserve, as detailed in section 5 of the report;
(v) Note the performance of
the Investment Acquisition Strategy (IAS) as set out in section 9
of the report;
(vi) Note that the
Capital Programme provisional outturn position for 2023/24 showed
an underspend of £5.405m against a revised budget of
£340.387m;
(vii) Approve the carry forwards
totalling £3.2m to the Capital Programme 2024/25, as detailed
in section 11 and Appendices B and C to the report; increasing the
capital budget for 2024/25 from £252.1m to £255.3m;
and
(viii) Note the update on the progress
on the year-end accounts and the work still outstanding, as set out
in section 12 of the report.
Supporting Documents