Brent Cross Update Report
March 3, 2025 Cabinet (Cabinet collective) Key decision Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to progress the Brent Cross Cricklewood Regeneration Programme, the Cabinet approved actions including noting progress on completed and ongoing construction, delegating authority to procure an operator for the Plot 13 Community Space, agreeing to award a contract for highway infrastructure works, and noting updates to the Strategic Communications and Engagement Plan and the Community Impact Framework.
Related Meeting
Cabinet - Monday 3rd March, 2025 7.00 pm on March 3, 2025
Supporting Documents
Details
| Outcome | For Determination |
| Decision date | 3 Mar 2025 |
| Effective from | 13 Mar 2025 |
| Expected date | 3 Mar 2025 |
| Originally due | 3 Mar 2025 |
| Subject to call-in | Yes |