The Executive Director of Children's Services approved the acceptance of a tender for structural repairs at Coppetts Wood School on 24/10/2025. The decision approved recommendations for structural repairs to the school's modular building. The works include the provision of supporting structural elements to correct bowing in the main roof beam and make good affected areas, to be completed by October 2025.

Full council record

Purpose

The
existing structural elements are showing signs of failure and
compromise structural stability. Consequently, it has been
prioritised in accordance with the Council’s Modernisation
Programme 2025/2026 and verified by the BELS and Estates / Building
Services Team of London Borough of Barnet.
The
design and specification were taken to provide structural stability
in affected areas. The main contractor was selected following
Procurement  mini competition
process  between LBB Term
Contractors.
 Works are scheduled to take place on site during
Summer holiday 2025 and to be completed by October 2025.

Supporting Documents

As cleared Delegated Powers Report - Coppetts Wood School Structural Repair Acceptance of Tender - C.pdf
Coppetts Wood School Structural Repair DPR.pdf
Appendix A- Annual Procurement Forward Plan APFP 2025-26 1.pdf

Details

OutcomeRecommendations Approved
Decision date24 Oct 2025