Brent Cross Cricklewood CPO Strategy Update

January 10, 2024 Deputy Chief Executive (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to progress the Brent Cross Cricklewood regeneration project, the council will issue confirmation letters for plots no longer pursued, serve entry notices for plots needed for infrastructure, extend Notices on Treat, vary existing or create new land agreements, and delegate authority to the Brent Cross Programme Director for plot list changes.

Full council record

Purpose

1.           
To authorise the issuing of confirmation letters
that the council will not be pursuing plots identified in Appendix
1

2.           
To authorise the serving of Notice to Entry for
Plots listed in Appendix 2, interests in land the council needs to
secure for infrastructure works planned to support the
project. 

3.           
To authorise the entering into extensions to the
Notices on Treat where required on appropriate terms to suit the
project requirements.

4.           
To authorise the Variation of existing
Undertakings or new Agreements around parcels of land required for
the infrastructure for the BXS programme for the
project.

5.           
To delegate to the Brent Cross Programme Director
approvals for any final changes to Appendix 1 or Appendix 2 for
deleting or adding plots should they be identified as required or
not for the project.

Decision

1.           
To authorise the issuing of confirmation letters
that the council will not be pursuing plots identified in Appendix
1

2.           
To authorise the serving of Notice to Entry for
Plots listed in Appendix 2, interests in land the council needs to
secure for infrastructure works planned to support the
project. 

3.           
To authorise the entering into extensions to the
Notices on Treat where required on appropriate terms to suit the
project requirements.

4.           
To authorise the Variation of existing
Undertakings or new Agreements around parcels of land required for
the infrastructure for the BXS programme for the
project.

5.           
To delegate to the Brent Cross Programme Director
approvals for any final changes to Appendix 1 or Appendix 2 for
deleting or adding plots should they be identified as required or
not for the project.

Supporting Documents

CPO Land Acquisition Strategy NoE Update.pdf
CPO Land Acquisition Strategy NoE Appendix 1 2.pdf

Details

OutcomeRecommendations Approved
Decision date10 Jan 2024