Authority to Vary Contract in Respect of Design and Build of the Additionally Resourced Provision (ARP) at Newman Catholic College with Morgan Sindall Construction & Infrastructure Ltd (Non-Key Officer Recordable Decision)
September 10, 2025 Director - Property and Assets (Other) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve a £375,447.11 variation to the contract with Morgan Sindall Construction & Infrastructure Ltd for the design and build of the Additionally Resourced Provision (ARP) at Newman Catholic College to address unforeseen ground conditions, asbestos removal, and additional school requirements.
Full council record
Purpose
To request authority to vary a contract in
respect of the design and build of the Additionally Resourced
Provision (ARP) at Newman Catholic College with Morgan Sindall
Construction & Infrastructure Ltd.
Content
That the Director Property and Assets:
i)
Approves the variation of the contract for the design and build of
the Additionally Resourced Provision (ARP) at Newman Catholic
College with Morgan Sindall Construction & Infrastructure Ltd
by £375,447.11 to deal with unforeseen ground conditions,
asbestos removal and additional school requirements.
Reasons for the decision
The Council entered into a contract for the
design and build of ARP at Newman Catholic College with Morgan
Sindall Construction and Infrastructure Ltd in November 2024.
Officers have concluded that the contract
requires variation to deal with unforeseen ground conditions,
asbestos removal and additional school requirements.
Alternative options considered
An alternative option would be to not vary the
contract and seek other contractors / suppliers to complete the
works. This option was discounted as it would involve additional
procurement activities which would have prevented other works from
progressing and led to significant delays to the project.
Details
| Outcome | Recommendations Approved |
| Decision date | 10 Sep 2025 |