Authority to vary contract in respect of design and build of the Additionally Resourced Provision (ARP) at St Margaret Clitherow RC Primary School with Morgan Sindall Construction & Infrastructure Ltd (non-key officer recordable decision)
November 12, 2025 Director - Property and Assets (Other) Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve a $488,606.12 contract variation with Morgan Sindall Construction Ltd for the design and build of the Additionally Resourced Provision at St Margaret Clitherow RC Primary School due to unforeseen ground conditions, asbestos removal, and external works.
Full council record
Purpose
To request authority to vary a contract in respect of the design and build of the Additionally Resourced Provision (ARP) at St Margaret Clitherow RC Primary School with Morgan Sindall Construction & Infrastructure Ltd.
Decision
That the Director of Property and Assets:
i) Approves the variation of the contract for the design and build of the Additionally Resourced Provision (ARP) at St Margaret Clitherow RC Primary School with Morgan Sindall Construction Ltd by $488,606.12 to deal with unforeseen ground conditions, asbestos removal and external works.
Reasons for the decision
The Council entered into a contract for the design and build of the Additionally Resourced Provision (ARP) at St Margaret Clitherow RC Primary School with Morgan Sindall Construction & Infrastructure Ltd in November 2024.
Officers have concluded that the contract requires variation to deal with unforeseen ground conditions, asbestos removal and additional school requirements.
Alternative options considered
An alternative option would be to not vary the contract and seek other contractors / suppliers to complete the works. This option was discounted as it would have involved additional procurement activities which would have prevented other works from progressing and led to significant delays to the project.
Details
| Outcome | For Determination |
| Decision date | 12 Nov 2025 |