Affordable Housing Supply update 2023
December 11, 2023 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Brent Cabinet approved recommendations on 11/12/2023 regarding affordable housing supply. The Cabinet agreed to award a main works contract for Church End, noted challenges with Morland Gardens and agreed officers would develop an alternative site strategy, and approved the use of capital reserves for the New Council Homes Programme. They also approved an acquisitions budget of £52.7m and a new delegation for the Corporate Director of Resident Services to acquire 133 homes from the open market.
Full council record
Purpose
To update the New Council Homes Programme and wider supply in the borough and across regeneration schemes.
To approve entry into the main works contract for Church End.
To review the South Kilburn Landlord offer for future temporary accommodation placement.
Leasing Arrangement Under Brent Direct Leasing Scheme - Manor Park, Manor Park Road, Harlesden, NW10 4JJ.
Decision
Cabinet RESOLVED:
(1) To agree to award the Main works contract to Wates for the delivery of Church End including 99 homes and a new market square for the value set out in Recommendation 1 of Appendix 1 of the report (which contained exempt information).
(2) To note the challenges set out regarding the delivery of Morland Gardens in paragraph 5.3 – 5.10 of the report and agree for officers to develop an alternative site strategy for future consideration by Cabinet.
(3) To approve, that if necessary, the Council consult on ending the South Kilburn Promise (Landlord Offer) for new temporary accommodation households and the use of voids properties identified on the South Kilburn regeneration area for temporary accommodation, noting the legal considerations around consultation set out in Section 8 of the report.
(4) To note the updated programme budget for the New Council Homes Programme of £495.5m and approve the use of usable Capital reserves to fund this.
(5) To agree to wave the delegated authority limits to enable the Corporate Director of Resident Services in consultation with the Corporate Director of Finance and Resources to agree the terms of the lease and thereafter enter into and complete on a 5-year leasing arrangement with the developer for the new build scheme at Manor Park Road, Harlesden NW10 4JJ for use as emergency and settled temporary accommodation, as set out in Section 6 of the report and where necessary make any further amendments as and when required.
(6) To approve an acquisitions budget of £52.7m to address the acute housing and temporary accommodation needs and challenges. This is in addition to any acquisitions already approved by Cabinet.
(7) To agree for a new delegation to the Corporate Director of Resident Services in consultation with the Corporate Director of Finance and Resources, to acquire 133 homes from the open market (including both freehold and leasehold acquisitions) such delegation to include negotiating and approving the terms of any freehold or leasehold acquisitions and thereafter entering into the relevant transactional documents to address the acute housing and temporary accommodation needs in line with approach set out in Section 11 and Appendix 1 (containing exempt information) of the report, which is in addition to those acquisitions already approved by Cabinet.
Eligible for call-in: Yes
Deadline for submission of call-in: 6pm on Monday 18 December 23
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 11 Dec 2023 |
| Effective from | 19 Dec 2023 |
| Subject to call-in | Yes |