To request approval to trigger the second
stage of the two stage design and build contract at Picture
Palace.

Content

That the Corporate Director Finance and
Resources:
 
i)            
Approves the award of the second stage of the two-stage design and
build contract with Ark Build Plc for the Picture Palace
refurbishment works for a sum of £3,188,879.39.