... whether to approve the release of various capital program budgets, totaling millions of pounds, for projects related to developer contributions, flood management, special school places, building repairs, bus services, and the Council's estate strategy.

Full council record

Purpose

To approve the release of Capital Programme budgets for projects that have progressed through the Capital Gateway

Decision

Recommendations:

(1)   To approve the addition to the Capital Programme of £2.62m of s106 developer contributions in 2025/26,  include contributions of £1.53m in Health, £882,000 in Transport and £211,000 in Open Spaces.

(2)   Approve the release of the above £2.62m budget to progress the agreed s106 schemes. 

(3)   To agree to progress the Buckinghamshire Great Ouse Natural Flood Management project and Property Flood Resilience Feasibility Study, including release of £410k existing capital budget, adding an additional £370k of external funding from the Environment Agency for the project and a feasibility study and re-allocate £40k from an unallocated Flood Capital budget as a match funding contribution

(4)    To approve the release of £1.18m of funding from the existing Special School Places funding block to progress proposals for the Chiltern Way Academy Trust

(5)   To approve the release of £135k funding from the existing Special School Places funding block to repurpose the former caretaker’s bungalow at Pebble Brook School for a SEND facility

(6)   To approve the release of £145k from the existing programme to finish the repair of Rowley Farm Barns

(7)   To approve the release of £4,210,555 Better Bus Grant capital funding from the existing programme to deliver the schemes and measures specified in the DfT Delivery Plan

(8)   To approve the release of £1.85m of Capital Contingency towards the Council’s invest-to-save Estate Strategy, as detailed in Confidential Appendix A.

Details

Decision date26 Sep 2025
Effective from4 Oct 2025
Subject to call-inYes