Capital Gateway – Green Ridge Primary Academy Expansion
February 19, 2024 Cabinet Member for Resources, Leader (Cabinet member) Key decision Approved View on council websiteFull council record
Purpose
To approve the release of £5,094,385
from the Primary Places funding block within the Capital Programme
to fund the one form entry expansion of Green Ridge Primary
Academy
Content
The
Leader:
APPROVED the release of £5,094,385 from the Primary Places
funding block within the Capital Programme to fund the one form
entry expansion of Green Ridge Primary Academy
This decision is being taken
under the ‘special urgency’ provisions of the
constitution in order to achieve a September 2024
completion/opening for the Schools of the additional classrooms;
and, to thereby save costs of temporary classrooms. The timelines to achieve this require the Council
to enter into contract with the main contractor (Morgan Sindall) by
20 February 2024
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Feb 2024 |