Authority to agree an easement to install high voltage electrical cables within Council owned land, Iver
August 9, 2023 Cabinet Member for Resources (Cabinet member) Key decision Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Cabinet Member for Resources agreed to authorise the Director for Property and Assets to enter a legal easement for high voltage cables. This decision was made on 09/08/2023. The easement will allow high voltage cables to be installed and utilised within Council-owned agricultural land at Iver.
Full council record
Purpose
The installation of an electrical connection between a new data centre in Slough and an existing electrical substation at Iver Heath. Part of the route crosses Mansfield Farm in Iver between Denham Road and Slough Road for which an easement is required
Decision
The Deputy Leader and Cabinet Member for Health and Wellbeing (on behalf of the Leader) AGREED to:
authorise the Director for Property and Assets in consultation with the Cabinet Member for Accessible Housing and Resources on behalf of the Council to enter a legal easement in line with the heads of terms attached to the report that would allow high voltage cables to be installed and utilised within Council owned agricultural land at Iver
Details
| Decision date | 9 Aug 2023 |
| Effective from | 15 Aug 2023 |