Q2 Capital Budget Adjustments and Reprofiling
November 26, 2024 Cabinet (Cabinet collective) Key decision Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve adjustments to the Capital Programme, including £10.237m in additions, £0.582m in reductions, a reprofile of £24.487m from 2024/25 to future years, and the release of £3.222m in project funding, resulting in a revised £686.639m Capital Programme.
Full council record
Purpose
Quarterly report
Decision
The Council’s Capital Programme for 2024/25 to 2027/28 was approved by Full Council in February 2024 as £666.264m. The programme was revised to £674.977m following additions agreed by Cabinet in July 2024. The report set out the recommended changes for approval and would result in the Capital Programme increasing to £686.639m. Since the Budget changes agreed by Cabinet in July 2024, £2.007m of additions have had Leader or Cabinet decision approval (Denmark Street Future High Street project, Disposal of Old County Offices, Aston Clinton Traffic Calming Phase 1, and the Libraries Transformation Programme).
The report recommended further changes which had been recommended through the Council’s Gateway process:
• Additions of £10.237m for new projects of which £5.187m are externally funded from grants and s.106, and £5.000m for additional roads funding is to be transferred from the Revenue budget, as originally approved at full council due to the Capital nature of the works, and a further £50k for Aylesbury Town Centre Improvement works funded from the Economic Reserve.
• Reductions of £0.582m, where external funding has been reviewed.
• A reprofile of the programme to align with current project delivery plans, including £24.487m is recommended to be reprofiled from 2024/25 to future years.
RESOLVED that the recommended changes to the Capital Programme be approved:
- £10.237m of additions to the Capital Programme, of which £5.187m are funded from ringfenced grants and s.106, and £5.050m is funded from ringfenced council reserves.
- £0.582m of technical adjustments from the capital programme for adjustments to external funding.
- The revised £686.639m Capital Programme, with £24.487m reprofiled from 2024/25 into future years.
- 4. the release of funding of £3.222m relating to the projects set out in section 5 of the report.
Related Meeting
Cabinet - Tuesday, 26th November, 2024 10.00 am on November 26, 2024
Details
| Decision date | 26 Nov 2024 |
| Effective from | 5 Dec 2024 |
| Subject to call-in | Yes |