Grant of Licence to Network Rail to have temporary use of an area of land at Central Park for a site compound in connection with track renewal works

November 26, 2024 Executive Director - Environment, Highways and Community Services (Officer) Approved View on council website
Full council record

Purpose

Network Rail are undertaking some track
renewal works in connection with the Station Improvement Scheme and
would like to use part of a plot at Central Park, adjacent to their
site access, for the parking of vans and cars plus temporary site
welfare facilities (cabin) and a tools cabin. The use is programmed
to commence on 6th January and last for 13 weeks
approximately.

Decision

The Council to grant a licence to Network Rail
from 6th January 2025 for a period of 15 weeks (includes overrun)
at a fee of £4,500.

To allow Network Rail to use the Council’s land on
appropriate terms.

Details

OutcomeRecommendations Approved
Decision date26 Nov 2024