Modification of Contract PLACE598ET Shipley Lake Design and Build Scour Pipe Installation
July 20, 2026 Cabinet Member for Environment (Cabinet member) Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Cabinet Member for Environment approved the modification of contract PLACE598ET Shipley Lake Design and Build Scour Pipe Installation on 20/07/2026. This approval ensures the scour pipe is fully installed to the required specification for sign off.
Full council record
Purpose
To seek the Cabinet Member’s approval to modify the current contract.
Decision
The Cabinet Member approved, in accordance with the Council’s Standing Orders and Financial Schedule of Delegation, the modification of the current contract.
Reasons for the decision
Approval to modify the current contract would ensure that the scour pipe is fully installed to the specification required to obtain sign off.
Alternative options considered
Option 1: Do Nothing - This option is not recommended.
Option 2: Proceed with an open tender to procure another contractor to undertake some of the additional work identified. This option is not recommended.
Option 3: Proceed with a procurement exercise to accommodate the additional work in parallel to the existing contract. This option is not recommended.
Option 4: Under the Council’s Standing Orders, seek approval to modify the current contract. This is the recommended option.
Details
| Reference | Call-ins0 |
| Outcome | For Determination |
| Decision date | 20 Jul 2026 |
| Effective from | 28 Jul 2026 |
| Subject to call-in | Yes |