Weymouth Harbour Wall 4 Improvement and Strengthening

September 5, 2023 Cabinet (Cabinet collective) Key decision Awaiting outcome View on council website
Full council record
Purpose

Authorisation
to appoint Hanson as the Contractor through their Highways Partnership Term
Contract on the basis that they are best placed to execute the work.

Content

(a)   
That the proposed repair, strengthening and
raising of Wall 4, in accordance with the estimate set out in section 2 of the
report, to meet the Council’s obligations to maintain appropriate sea defences
and harbour wall requirements, be agreed.

 

(b)   
That authority be delegated to the Executive
Director for Place, in consultation with the Portfolio Holder for Highways,
Travel and Environment, to appoint a contractor through the Highways
Partnership Term Contract to undertake the work.

 

(c)   
That authority be delegated to the Executive
Director for Place, in consultation with the Portfolio Holder for Levelling Up,
to approve construction related spend (following receipt of an acceptable
quotation) with funds from the Levelling Up bid in terms of which £1.5m has
been allocated to Wall 4 replacement.

 

Reason for the decision

 

The Weymouth Harbour Wall 4 Improvement and Strengthening
project constitutes necessary work on a wall that has reached the end of life
and must be reinstated or rebuilt for the Council to properly discharge its
duty to the public, the harbour, and the associated coastal sea defences.

Supporting Documents

Appendix 1 - Weymouth Harbour Wall 4 Locality Plan.pdf
Weymouth Harbour Wall 4 Improvement and Strengthening.pdf

Details

OutcomeFor Determination
Decision date5 Sep 2023
Effective from14 Sep 2023
Subject to call-inYes