Solar PV Installations using Salix Finance Loan
June 12, 2024 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve a £1,000,000 two-phase program, funded by a Salix Finance loan, for the design, supply, and installation of photovoltaic solar panels across the Gloucestershire County Council estate, allocating £550k for the initial phase at eleven specific properties and £450k for a subsequent phase, while delegating authority for further business case approvals and procurement to the Executive Director of Corporate Resources.
Full council record
Purpose
To seek approval for a £1,000,000 two phase programme for the delivery of photovoltaic solar panels across the GCC estate.
Decision
Cllr David Gray sought Cabinet approval for a £1,000,000 two phase programme for the delivery of photovoltaic solar panels across the GCC estate.
Having considered all of the information, Cabinet noted the report and
RESOLVED to:
- Approve the use of £550k for the purpose of part funding the contract(s) described in Recommendation 3(b) relating to the design, supply and installation of
photovoltaic solarpanels at the following eleven GCC- owned properties during the initial phase of the programme described in paragraph 2 of this report (the “PV Panel Programme"):
a. Quedgeley Library, Gloucester
b. Lydney Library
c. Newent Library
d. Whaddon Youth Centre, Cheltenham
e. Cheltenham Library
f. Hesters Way Library, Cheltenham
g. Oakwood Children's Centre, Cheltenham
h. Gloucestershire Heritage Hub, Gloucester
i. Coroners Court, Gloucester
j. Tewkesbury Youth Support Centre
k. The Vibe, Coney Hill, Gloucester
- Approve the use of £450k for the purpose of funding a further phase of the PV Panel Programme under the contract(s) described in Recommendation 3(b).
- Delegate authority to the Executive Director of Corporate Resources, in consultation with the Cabinet Member for Environment and Planning and the Deputy Leader/Cabinet Member for Finance and Change to:
a. Approve business cases for the design, supply, and installation of Solar PV panels (with or without battery storage), as part of the second phase of the PV Panel Programme, provided the total value of such works does not exceed £450k and that the works are in line with the council’s and Salix’s (i.e., the loan provider’s) approved Return on Investment and best value obligations.
b. Conduct a competitive procurement process in respect of contract(s) for the design, supply and installation of solar PV panels (with or without battery storage) under both phases of the PV Panel Programme
c. Awards such contract(s) to the preferred tenderer.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 12 Jun 2024 |
| Effective from | 20 Jun 2024 |
| Subject to call-in | Yes |