The procurement of highway services and construction phase works in connection with the delivery of Forest Road Lydney Geotechnical Stabilisation Scheme.
September 17, 2025 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to allow the Assistant Director of Highways and Infrastructure, in consultation with the Cabinet Member for Highways Maintenance, to procure highway services and construction for the Forest Road Lydney Geotechnical Stabilisation Scheme, award the contracts, and make necessary traffic regulation orders.
Full council record
Purpose
To seek delegated authority to:
1. Procure highway services and construction phase works, through a
competitive tender process, in relation to Forest Road Lydney
Geotechnical Stabilisation Scheme; and
Make such ancillary orders as are necessary to successfully
implement the said scheme.
Decision
Cllr Joe Harris sought delegated
authority to procure highway services and construction phase works,
through a competitive tender process, in relation to the Forest
Road Lydney Geotechnical Stabilisation Scheme and then make such
ancillary orders as are necessary to successfully implement the
said Scheme.
Having considered all of the information,
Cabinet noted the report and
RESOLVED to:
Delegate authority to the
Assistant Director of Highways and Infrastructure, in consultation
with the Cabinet Member for Highways Maintenance, to:
1.
Conduct a competitive procurement process in respect
of as many contracts as may be required for the supply of highway
services and construction phase works in relation to the Forest
Road Lydney Geotechnical Stabilisation Scheme (the
“Scheme”);
2.
Award the above contract(s) to the preferred
tenderer(s); and
3.
Make such ancillary traffic regulation orders as may
be required in order to successfully implement the Scheme, (such as
temporary traffic regulation orders (TTROs) for speed limits etc.)
during the construction phase of the Scheme.
Related Meeting
Cabinet - Wednesday 17 September 2025 10.00 am on September 17, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 17 Sep 2025 |
| Subject to call-in | Yes |