B4234 Forest Road, Lydney Geotechnical Remediation – Additional Works at Sites 1a and 2

August 11, 2026 Cabinet Member - Highways (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Assistant Director of Asset Management and Property Services Kurtis Lee awarded a works contract to Snape Contracting on 12/06/2026. The contract is for the supply of an additional bedroom to a private homeowner's property with a maximum cost of £115,200.

Cabinet Member for Highways Councillor Mark Harris commissioned additional construction works at B4234 Forest Road, Lydney Sites 1a and 2 on 11/08/2026. This decision amends the existing contract scope with Montel Civil Engineering Ltd for the B4234 Forest Road Geotechnical Stabilisation Scheme.

Full council record

Purpose

To seek delegated authority to procure highways services and construction phase works, through the existing construction contract in place with Montel Civil Engineering Ltd, in relation to Forest Road, Lydney Geotechnical Stabilisation Scheme.

Decision

That the Cabinet Member for Highways rejects the alternative options and takes the recommended decision to:

Commission additional construction works at B4234 Forest Road, Lydney Sites 1a and 2 by making an amendment to the existing contract scope with Montel Civil Engineering Ltd for the B4234 Forest Road Geotechnical Stabilisation Scheme

For the reasons set out in the report.

Supporting Documents

For Publication - FINAL Notice of Urgent Decision General Exception Rule - Forest Road Lydney.pdf
For Publishing - FINAL B4234 Forest Road Lydney Geotechnical Remediation at Sites 1a and 2 ICM Repor.pdf
For Publication - AMPS executive decisions foster care pilot project.18.6.26 - Copy.pdf
For Publication - EqIA - Forest Road Additional Sites.pdf
ICM Decision Statement - Forest Road Lydney GER signed.pdf
For Publication - AMPS executive decisions foster care pilot project.18.6.26 - Copy.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date11 Aug 2026
Effective from19 Aug 2026
Subject to call-inYes