Summary

The Planning Board of Greenwich Council decided to grant full planning permission for the demolition of an industrial warehouse and the erection of a new building for flexible uses. This decision was made on 21 October 2025. The approval is subject to the completion of a Section 106 legal agreement and specified conditions, including consideration of a crossing across Kellner Road.

Full council record

Decision

Resolved that full planning
permission be granted for the demolition of
existing industrial warehouse and erection of building for flexible
uses under Use Classes E(g)(iii), B2, and B8, including associated
car and cycle parking, EV charging points, substation, service
areas, hard surfacing, landscaping, means of enclosure and
utilities.
 
Consent subject
to:

·     
The completion of a satisfactory Section 106 (S106)
Legal Agreement (obligations set out in Section 25 of the report)
with amendment –

‘to include consideration of a crossing across
Kellner Road between the Ridgeway and the application site

·     
The Conditions set out in Appendix 2 of the
report.
 
That the Assistant Director
(Planning & Building Control) be authorised to:

·     
Make any minor changes to the detailed wording of
the recommended conditions as set out in Appendix 2 of the report,
and the minutes of this Planning Board meeting, where the Assistant
Director (Planning & Building Control) considers it
appropriate, before issuing the final decision notice

·     
Finalise the detailed terms of the section 106
agreement (including appended documents) and form of the planning
obligations as set out in Section 25 of the report and the minutes
of this Planning Board meeting

·     
Consider, in the event that the Section 106
Agreement is not completed within three (3) months of the date of
this Planning Board resolution, whether consent should be refused
on the grounds that the agreement has not been completed within the
appropriate timescale, and that the proposals are unacceptable in
the absence of the recommended planning obligations; and if the
Assistant Director (Planning & Building Control) considers it
appropriate, to determine the application with reasons for refusal
which will include the following:
§ 
In the absence of a legal agreement to secure the
necessary obligations regarding , transport and highway works,
public transport enhancements, 
employment and training, equal opportunities and energy and
sustainability the development would fail to mitigate its impact on
local services, amenities and infrastructure, environmental
sustainability and open space contrary to policies H1, H4, H5, H7,
H8, S2, SI 2, SI 3, T2, T4, T9 and DF1 of the London Plan (2021)
and H3, H5, H(e), EA4, EA(c), OS1, E1, CH(a), IM1, IM4, IM(a) and
IM(b) of the Royal Greenwich Local Plan: Core Strategy with
Detailed Policies (Adopted July 2014), and the Planning Obligations
(s106) Guidance SPD (July 2015).
 

Related Meeting

Planning Board - Tuesday, 21st October, 2025 6.30 pm on October 21, 2025

Supporting Documents

Appendieces to 138-140 Nathan Way - Ref 25.2323.F.pdf
138-140 Nathan Way - Ref 25.2323.F.pdf

Details

OutcomeRecommendations Approved
Decision date21 Oct 2025