Report of Programme Manager, Capital Projects & Property Maintenance
June 23, 2026 Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Eltham Crematorium Joint Committee on 23 June 2026 noted the progress of the 3-year works programme and agreed to a £25,000 programmed maintenance regime for small ponds. They also noted that works programmed for 2026/7 have been deferred, with only retention payments scheduled for release.
Full council record
Decision
Noted the progress of the 3-year works programme included as Appendix 1 of the report.
Noted that as agreed at the last meeting on 4th February 2026 all works programmed for 2026/7 have been deferred and the only programmed spend in 2026/7 is the release of retention for works completed in 2025/6 in the sum of £24,702.33.
Agreed that the small ponds in the North Chapel and memorial garden would benefit from a face lift and programmed maintenance regime similar to that put in place for the large pond, costs for such a regime in 2026/7 are estimated at £25,000.
Noted the content of the feasibility study (appendix 2 of the report) into cremator replacement and discuss planned date for replacement programme.
Related Meeting
Eltham Crematorium Joint Committee - Tuesday, 23rd June, 2026 6.30 pm on June 23, 2026
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 23 Jun 2026 |