Capital Programme Monitor and Budget Variations, 2024/25 (Outturn)

September 15, 2025 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to note the capital outturn for the year of £253.1m, approve budget variations to the capital programme from 2024/25 to 2027/28, approve an additional £5m budget for pre-agreed works within the HRA asset and compliance programme funded by HRA borrowing, and note the additional budget approved by Full Council on 7th October 2024 for the Hammersmith Town Hall refurbishment funded by General Fund borrowing.

Full council record

Purpose

The report provides details of the capital
programme outturn for the financial year 2024/25 (including the
financing of this spend

Decision

1.   
To note the capital outturn for the year of
£253.1m.
 

2.   
To approve the proposed budget variations to the
capital programme (2024/25 to 2027/28) as summarised in Tables 1
and 5 and detailed in Appendix 1.
 

3.   
To approve an additional £5m budget in
relation to pre–agreed works within the HRA asset and
compliance programme, funded from HRA borrowing.
 

4.   
To note the additional budget as approved by Full
Council on 7th October 2024 for the Hammersmith Town Hall
refurbishment, funded from General Fund borrowing.

Related Meeting

Cabinet - Monday, 15th September, 2025 7.00 pm on September 15, 2025

Supporting Documents

Capital Programme Monitor and Budget Variations 2024-25.pdf

Details

OutcomeRecommendations Approved
Decision date15 Sep 2025
Subject to call-inYes