Appointment of Design Team for the Four Sites at: Barclay Close, Becklow Gardens, Land Behind the Grange, Land Adjacent to Jepson House
March 21, 2024 Cabinet Member for the Economy (Cabinet member) Key decision Approved View on council websiteFull council record
Purpose
Following the procurement process. This report
will seek approval to appoint the design team for the four
sites.
Decision
The Cabinet Member for the Economy
is recommended to:
1.
Approve that Appendix 1
and 2 are not for publication on the basis that they contain
information relating to the financial or business affairs of any
person (including the authority holding that information) as set
out in paragraph 3 of Schedule 12A of the Local Government Act 1972
(as amended).
2.
Approve the appointment of PRP Architects LLP to
provide professional ‘Design Team’ services consisting
of:
* Lead Architect
* Lead Designer (to coordinate design)
* Planning Consultant
* Landscape Architect
* Structural and Civil Engineers
* M&E Consultant
* Sustainability & Energy Consultant
* Plus some proprietary survey work (geotechnical
assessment, prelim ecological appraisal, arboricultural impact assessment and
others)
The newly required Building Safety Act (BSA)
Principle Designer (PD) role will be
commissioned under a separate procurement exercise and be appointed
to sit within the ‘client
tram’, independent from other
‘designers’.
The Design Team are to redevelop each of the four
independent sites through Gateways 2 –
Planning and 3 – Procurement (RIBA Stages 1 – 4) of the
Council’s Development Gateway process. The Headline Programme
up to Planning is shown below.
Milestone
Date
LBHF Development Stage 2:
(Planning)
?
RIBA Work Stages 1
Mar 24
RIBA Work Stages 2
Mar – Aug 24
RIBA Work Stages 3
Sep 24 – Dec 24
Planning Submission
Jan 25
RIBA Stage 3+ Supplementary Design
Jan 25 – Mar 25
RIBA Stage 4 Procurement
Mar 25-Nov 25
Planning Consent
May 25
3.
To note individual budget allocations including 10%
contingency (at a total of £1,922,008) from the existing
budget envelope as set out below:
i)
Barclay Close for a value of
£351,983.50
ii)
Becklow
Gardens for a value of £477,582.88
iii)
land behind the Grange for a value of
£417,859.75 and
iv)
land adjacent to Jepson House for a value of
£674,581.88
4.
To note that this sets the build standard to
aspirational on all four projects combined, with all four projects
independent of each other.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 21 Mar 2024 |
| Subject to call-in | Yes |