Capital Programme Monitor & Budget Variations, 2023/24 (Third Quarter)
February 12, 2024 Cabinet (Cabinet collective) Key decision Approved View on council websiteFull council record
Purpose
This report provides a financial update on the
council’s capital programme and requests approval for budget
variations to the capital programme.
Decision
1.
To note the net increase in forecast capital expenditure of
£4.9m for 2023/24.
2.
To approve the updated four-year capital programme for 2023-2027 of
£706.7m as detailed in Appendix 1.
3.
To approve £16.984m additional pre-financing with regards to
Hammersmith Bridge stabilisation (£7.927m) and
pre-restoration (£9.057m) works, funded from the General Fund
borrowing. Much of this will be reclaimed from TfL and
Government.
4.
To approve £0.5m additional budget with regards to Mund
Street refurbishment costs, funded from the General Fund
borrowing.
5.
To approve £0.54m additional budget for Avonmore
predevelopment costs, funded from the General Fund borrowing.
6.
To note the potential risks regarding the General Fund Programme,
as summarised in paragraphs 25-29.
7.
To note the potential risks regarding the Housing Capital
Programme, as summarised in paragraphs 30-33.
8.
To note prudential indicators presented in Appendix 5, as per
Prudential Code requirements.