Leisure Operating Contract Modification to include Capital Works at Lillie Road Fitness Centre
June 19, 2023 Cabinet Member for Public Realm (Cabinet member) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to modify the Leisure Operating Contract with Greenwich Leisure Limited to include a £355,000 roof replacement at Lillie Road Fitness Centre, funded through borrowing.
Full council record
Purpose
Replacement of Lillie Road Recreation Centre
roof , using the existing operating Contractor GLL to carry out the
works.
Decision
1.
To modify the Leisure Operating Contract dated 25
March 2021 between LBHF and Greenwich Leisure Limited, to include
works to replace the roof at Lillie Road Fitness Centre at a total
cost not exceeding £355,000.
2.
To enter into a Deed of Variation and any ancillary
documents necessary to give effect to the decision at
recommendation 1.
3.
To fund the capital works from borrowing, up to a
maximum of £355,000 in 2023/24.
Reasons for the decision
The roof at Lillie Road Fitness
Centre is damaged beyond repair, and in need of
replacement.
Alternative options considered
a.
Do nothing (not recommended)
b.
Repair the roof (not recommended)
c.
Replace the roof (recommended)
This is the only viable
option; it would prolong the life of the building and allow
residents to continue to use a vital service that promotes good
health and wellbeing. This is also the most cost-effective
solution.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Jun 2023 |
| Subject to call-in | Yes |