Capital Programme Monitor and Budget Variations 2025/26 (Quarter 3)

April 13, 2026 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Cabinet of Hammersmith and Fulham approved the capital programme monitor and budget variations for 2025/26 on 13/04/2026. They noted the overall forecast of £220.8m for 2025/26 capital expenditure, approved a total additional investment of £3.7m across the revised four-year programme, and approved the updated four-year capital programme for 2025-2029 of £657.776m.

Full council record

Purpose

This report provides a financial update on the council’s capital programme and requests approval for budget variations to the capital programme.

Decision

  1. To note the overall forecast of £220.8m for 2025/26 capital expenditure which is a net decrease of £45m in comparison to the revised budget of £265.3m at Q2 2025/26.
  1. To approve a total additional investment of £3.7m across the revised four-year programme, including new additional borrowing, the details of this investment are set out in Appendix 1.
  1. To approve the updated four-year capital programme for 2025-2029 of £657.776m, as detailed in the report. This is a net increase of £3.7m in comparison to the forecast four-year programme as at Q2 2025/26 (£654.026m).

Related Meeting

Cabinet - Monday, 13th April, 2026 7.00 pm on April 13, 2026

Supporting Documents

Capital Programme Monitor 2025-26 Quarter 3.pdf

Details

OutcomeRecommendations Approved
Decision date13 Apr 2026
Effective from18 Apr 2026
Expected date13 Apr 2026
Originally due13 Apr 2020
Lead officerJames Newman
Subject to call-inYes