Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)

October 12, 2026 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Cabinet of Hammersmith and Fulham Council decided to approve the updated four-year capital programme for 2026-2030 of £532.1m on 12 October 2026. They also noted the overall forecast of £209.3m for 2026/27 capital expenditure and approved a £12.9m change in investment across the programme.

Full council record

Purpose

This report provides a financial update on the Council’s capital programme and requests approval for budget variations to the capital programme.

Decision

  1. To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparison to the revised budget of £260.5m at 2025/26 outturn.
  1. To approve the overall change in investment of £12.9m across the revised four year programme, including new additional borrowing. Details of this investment are set out in Appendix 1.
  1. To approve the updated four-year capital programme for 2026-2030 of £532.1m, as detailed in the report. This is a net decrease of £12.9m in comparison to the forecast four-year programme as at outturn 2025/26 (£545m).

Related Meeting

Cabinet - Monday, 12th October, 2026 6.30 pm on October 12, 2026

Supporting Documents

Capital 2026-27 Q1 - Final.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date12 Oct 2026
Effective from17 Oct 2026
Expected date12 Oct 2026
Originally due12 Oct 2026
Subject to call-inYes