Fire Door Installation Programme (Phase 1)

October 7, 2024 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve a procurement strategy for a mini-competition via the Fusion 21 framework to award a contract for phase 1 fire door installation works across the borough.

Full council record

Purpose

To ensure that we are compliant with UK fire
safety laws, the Fire Safety Works team have identified the need to
under a comprehensive program to install and upgrade fire doors
across the borough. This programme will involve works to
approximately 1682 residential blocks containing circa 11,735
doors. This programme will also place an emphasis on 247 high-rise
buildings which contain five stories or more as legislation
requires to prioritize these properties.

To manage this programme, we propose awarding a contract to work
through two thirds of our phase 1 plan. This relates to 2800 doors
(which is 67% of the total 4161 doors identified in phase 1). The
cost is projected at a total of 7 million pounds.

To source a contractor to undertake these works, we are seeking
approval to undertake a mini competition via the Fusion 21 Building
Safety and Compliance Framework, ‘Passive Fire Protection -
Fire Doors’ category. We are anticipating starting these
works by the end of summer 2024.

Decision

To note that Appendix
1 is not for publication on the basis that it contains information
relating to the financial or business affairs of any particular
person (including the authority holding that information) as set
out in paragraph 3 of Schedule 12A of the Local Government Act 1972
(as amended).

 

For Cabinet to
approve the procurement strategy to undertake a mini-competition
via the Fusion 21, Building Safety and Compliance Framework,
‘Passive Fire Protection - Fire Doors’ category for
works relating to phase 1 Fire Door Works.

 

Related Meeting

Cabinet - Monday, 7th October, 2024 7.00 pm on October 7, 2024

Supporting Documents

Procurement Strategy Report Fire Door Installation Programme.pdf

Details

OutcomeRecommendations Approved
Decision date7 Oct 2024
Subject to call-inYes