Major Works Programme Broadwater Farm Estate

August 10, 2026 Cabinet Member Signing (Cabinet member) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Cabinet Member Signing of Haringey Council approved a variation to the contract sum and programme for the Broadwater Farm External Major Works Programme on 10 August 2026. This included approving the anticipated final account position, principal cost drivers, and commercial controls. The decision also approved concrete repairs, balcony waterproofing, internal flooring renewal, sandblasting, drainage repairs, and redecorations using an A2 fire-rated coating.

Full council record

Decision

DECLARATIONS OF INTEREST FOR THIS ITEM:

NONE

RESOLVED

It was recommended that the Cabinet Member:

Approve pursuant to Contract Standing Orders CSO 2.01(d), 2.01(e) and 18.03.3, the variation to the contract sum and programme for the Broadwater Farm External Major Works Programme, as set out in Appendix A (Exempt Report).

Approve the anticipated final account position, including the principal cost drivers arising from regulatory, technical and contractual requirements, and the commercial controls applied to ensure value for money, as set out in the report.

Reasons for decision

The BWF - External Major Works Programme was brought forward to prevent further deterioration of key external and some internal building elements while the estate?wide refurbishment programme is developed and delivered. 

Works had been identified to eight blocks on the estate and included concrete repairs, balcony waterproofing, renewal of flooring to internal areas, sandblasting to remove existing paint from concrete elements, drainage repairs, and redecorations using an A2 fire-rated coating. These works would ensure the buildings remain safe, weather-tight, and compliant with current fire-safety regulations, helping to prevent increased safety risks, accelerated asset deterioration, and additional pressure on the responsive repairs budget.

Alternative options considered

Do nothing: This option was considered but discounted. A contractor had already been appointed, and works were currently in progress. Any delay in approving the variation to the contract sum and programme would leave the eight blocks incomplete, which would negatively affect the condition of the buildings and lead to further deterioration of key building elements.

Failure to approve the variation would also result in continued water ingress from the balconies, which in turn would lead to increased resident dissatisfaction due to the ongoing issues affecting the blocks.

The project team also considered pausing the works and completing them as part of the full estate regeneration. This option was discounted due to the lengthy timescales associated with the wider regeneration programme and the unacceptable risk of continued deterioration of the blocks during the interim period.

Supporting Documents

BWF External Major Works Programme Variation FINAL.pdf

Details

OutcomeRecommendations Approved
Decision date10 Aug 2026