Langstone FCERM Scheme - Planning and Consenting Phase

March 6, 2024 Cabinet (Cabinet collective) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...the Cabinet approved the continued progression of the Langstone FCERM Scheme to complete the Planning and Consenting management stage, while also supporting efforts to close the project's funding gap and endorsing collaboration with partner agencies, including a letter from the Leader to National Highways seeking their support.

Full council record

Decision

RESOLVED that:

  1. the continued progression to complete the Planning and Consenting management stage of the project (estimated cost £300k - £400k) be approved.
  2. the continued work to close the project’s remaining funding gap, while also seeking to decrease costs where possible, and seek certainty over the release of allocated funds, and cost benefit ratios from the Environment Agency be approved.
  3. the need to work with partner agencies to deliver this priority project for the borough be endorsed and in doing so, the Leader shall write to National Highways to express the need for their support.

Supporting Documents

Appendix B Wider Benefits Assessment 2019.pdf
Langstone Cabinet Report.pdf
Appendix A - Present day and future 1200 yr. flood mapping.pdf
LInks to Appendix C Preferred Option Report April 2019 and Appendix D Langstone Exhibition Pos.pdf
Appendix E Summary public consultation feedback.pdf

Details

OutcomeRecommendations Approved
Decision date6 Mar 2024
Effective from13 Mar 2024
Subject to call-inYes