Building / Fire safety Works
April 9, 2025 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to procure a contract for essential building safety works on high-risk council buildings, using a two-stage tender process via the Fusion 21 framework, with a modified evaluation criteria prioritizing quality and social value, and delegating award approval and procurement route changes to the Strategic Director of Place.
Full council record
Purpose
Approval to go to tender to procure a contract to
delivery these essential Building safety works.
This decision will be made under General
Exception provisions as it will have less than 28 clear days'
notice on the Forward Plan.
Decision
Cabinet:
1.
Approved the procurement of a
two-stage tender
process via
Lot 1 of the Fusion 21 Refurbishment, Construction,New Build and Modular
Buildings Framework
for building
safety remedial/improvement works to the
Council’s high-riskbuildings,comprising Pre-Construction
Services (Stage 1) and Works (Stage 2), with a total indicative value of
£13.4
million.
2.
Approved a waiver of the Council’s
default evaluation criteria of 70% Price: 30% Quality and instead
award the contracts on the MEAT basis of a 60% Quality, 30% Price,
and 10% Social Value weighting for the reasons set out in Section 4
of this report, Procurement
Proposals.
3.
Delegatedthe approval of the award of the
Pre-Construction Services Agreement (Stage 1) and the works
contract (Stage 2) to the Strategic Director of Place, acting in
consultation with the Strategic Director of Resources and the
Deputy Director of Legal & Governance.
4.
Delegated the change of procurement route from
a framework to a Dynamic Procurement system
(DPS),
if required, to the Strategic Director of
Place.
Related Meeting
Cabinet - Wednesday, 9th April, 2025 7.00 pm on April 9, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 9 Apr 2025 |
| Subject to call-in | Yes |