Highfield Towers Phase 1 - renewal of cladding
April 9, 2025 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve a two-stage tender process for the £7.5 million Highfield Towers Phase 1 cladding renewal project, including pre-construction services and works, using the LHC Fire Safety framework with a modified evaluation criteria prioritizing quality and social value, and delegating contract award and procurement route changes to the Strategic Director of Place.
Full council record
Purpose
Approval to seek tenders for the works to
renew the cladding.
Decision
Cabinet:
a)
Approvedin principle the procurement of a two stage tender to
replace the rainscreen
cladding,AOVs,
windows and roofing and
install sprinklers and LD1 fire alarms at
Highfield Towers comprising Pre-Construction Services (Stage 1) and
Works (Stage 2) utilising the LHC –
Fire Safety (FS2) Lot 7A framework with a combined indicative value of
£7.5Million.
b)
Approved a waiver of the Council’s
default evaluation criteria of 70% Price: 30% Quality and instead
award the contracts on the MEAT basis of a 60% Quality, 30% Price, and 10% Social
Value weighting for the reasons set out in Section
7 of this report, Procurement
Route.
c)
Delegated the approval of the award
of the Pre-Construction Services Agreement (Stage 1) and the works
contract (Stage 2) to the Strategic Director of Place, acting in
consultation with the Strategic Director of Resources and the
Deputy Director of Legal &
Governance.
d)
Delegated the change of procurement route from
a framework to a Dynamic Procurement system
(DPS),
if required, to the Strategic Director of
Place.
Related Meeting
Cabinet - Wednesday, 9th April, 2025 7.00 pm on April 9, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 9 Apr 2025 |
| Subject to call-in | Yes |