Cambridge Road Estate (CRE) - Variation to Project Agreements
June 17, 2025 People Committee (Committee) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to address requirements of the Building Safety Act, update affordable housing and handover requirements, amend the GLA loan terms, update LLP lease surrender terms, and allow for freehold transfer of private houses on the Cambridge Road Estate (CRE), the Committee agreed to variations to the RBK (Cambridge Road) LLP project documents and delegated authority to finalize and enter into a Deed of Variation and updated Power of Attorney.
Full council record
Content
RESOLVED that –
1.
The proposed variations to the RBK (Cambridge Road) LLP project
documents be agreed to address the following requirements:
a)
the incorporation of the requirements of the new Building Safety
Act
b)
Updates to RBK’s Affordable Housing and Handover
requirements
c)
amendments relating to the GLA loan
d)
Updates to the terms of the LLP lease surrender
e)
the need to allow for the freehold transfer of private houses;
2.
Authority be delegated to Executive Director Place, in consultation
with the Portfolio Holder for Housing, to finalise the wording of
and enter into a Deed of Variation/Supplemental Agreement to
crystalise the changes to the Project
Documents;
3.
Approval be granted to enter into the updated Power of
Attorney;
4.
Delegated authority be approved for the Executive Director of Place
to approve and enter into any future amended Power of Attorney
where this is required solely as a result of substitution of named
officers.
Related Meeting
People Committee - Tuesday 17 June 2025 7:30 pm on June 17, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 17 Jun 2025 |
| Subject to call-in | Yes |