Revenue and Capital Budget Monitoring 2025/26 as at Month 4

September 30, 2025 Corporate and Resources Committee (Committee) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...capital budgets were approved or increased for various projects, including the Local Implementation Plan, Highways and Transportation, acquisition of properties from Cambridge Road Estate LLP, Small Sites Phase 2 development programme, Disabled Facilities Programme, Hook Flood alleviation scheme, HRA Voids Works, Community Parks Programme, and NEC Housing system implementation, while also approving the reprofiling of other capital budgets.

Full council record
Content

NOTED:
 
1)      
the forecast outturn position in respect of the General Fund for
2025/26.
 
2)      
the forecast position on the Housing Revenue Account.
 
3)      
the forecast position of the Schools Budget and the Dedicated
Schools Grant (DSG) for 2025/26.
 
4)      
the forecast outturn position in respect of the Capital Programme
for 2025/26.
 
RESOLVED that:
 
5)      
a capital budget in 2025-26 of £0.7m for the Local
Implementation Plan be approved;
 
6)      
a capital budget in 2025-26 of £0.54m for the Highways and
Transportation be approved;
 
7)      
subject to GLA Grant funding approval, a capital budget of
£20.54m to support the acquisition of 55 properties from
Cambridge Road Estate LLP be approved;
 
8)      
a capital budget of £0.78m to initiate the Small Sites Phase
2 development programme be approved;
 
9)      
a capital budget increase in 2025/26 for the Disabled Facilities
Programme of £1.01m be approved;
 
10)   
a capital budget increase of £1.35m for the Hook Flood
alleviation scheme be approved;
 
11)   
 a capital budget increase for the HRA
Voids Works of £2.28m be approved;
.
12)   
a capital budget increase for Community Parks Programme of
£0.66m be approved;
 
13)   
an HRA capital budget increase for the NEC Housing system
implementation of £1.16m be approved;
 
14)   
the re-profiling of a number of capital budgets, which has the
effect of decreasing capital budgets by £54.55m in 2025-26
and increasing capital expenditure budgets by £45.27m over
the three year period 2026/27-2028/29
and noting an overall underspend of £9.28m as outlined in
Annex 1 be approved.

Supporting Documents

Annex 1 - Capital Budget Reprofiling 2025-26 as at Month 4 31 July 2025.pdf
Revenue Capital Budget Monitoring Report as at Month 4 31 July 2025.pdf

Details

OutcomeRecommendations Approved
Decision date30 Sep 2025