Proposed Amendments to the Highways Capital Programme – Street Lighting 23-24, & 24-25 Structural Testing Programme
November 26, 2024 Director of Highways and Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to reallocate funds within the Street Lighting Defects Programme to meet emerging priorities and allow completed projects to be closed out, without changing the overall budget.
Full council record
Purpose
As part of the normal process of service delivery, the approved highways capital programme now requires amendments to the street lighting programme to meet emerging priorities.
Head of Service is asked to approve the reallocation of funds within the Street Lighting Defects Programme. Details of the proposed reallocation is shown in appendix A. There is no change to the total budget.
It is proposed to reallocate funds within the programme to allow completed projects to be closed out.
The financial implications of the proposed changes detailed in the report can be accommodated within the overall approved programme allocations. There is no change to the overall budget. Details of the proposed changes in the programme are set out in the tables below. This item does not require cabinet approval.
Decision
Ridwan Musa, Head of Service Highway Operations and Design, on behalf of Matt Townsend, Director of Highways and Transport, took a decision to reallocate the funds within the Street Lighting Defects Programme, as outlined in the report.
Details
| Outcome | Recommendations Approved |
| Decision date | 26 Nov 2024 |