Addressing Overspend 19/20 Incentive Fund Programme

July 24, 2024 Director of Highways and Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to address overspending on the 19/20 Incentive Fund Programme, underspends from Moss Hey Lane, PBI's Package B, Hargreaves and Turpin PTSI's will be used to offset overspends for Tower Lodge, PBI's Package A, and Centenary Way.

Full council record
Purpose

Overspends have been recorded on the projects
with the 19/20 Incentive Fund Programme coloured red in the
attached report. The projects have overspent as a result of:
19/20 Centenary Way PTSI - Actual Outturn slightly higher cost than
estimate, slightly above normal tolerance for the framework
(8%).
19/20 PBIs Package A Lancashire East - Actual Outturn slightly
higher cost than estimate but still within tolerance (3%).
19/20 Tower Lodge Retaining Wall – Actual works required
larger than scope. Additional works required to stabilise scour.
Works are still ongoing but have been funded in subsequent years by
the Maintenance Budget.

It is proposed to offset these with underspends from the projects
coloured yellow in the attached report.

Content

A decision was made that from the 19/20 Incentive
Fund Programme that the underspends from: Moss Hey Lane, PBI's
Package B, Hargreaves and Turpin PTSI's be used to offset the
overspends for Tower Lodge, PBI's Package A and Centenary
Way.
 

Supporting Documents

Apendix A.pdf
Report.pdf

Details

OutcomeRecommendations Approved
Decision date24 Jul 2024