Provision of works at Burnley Town to Turf to include laying of paving at Yorkshire Street West.
April 17, 2024 Director of Highways and Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to award a contract to Holderness Groundworks & Paving Ltd to complete paving works at Yorkshire Street West in Burnley Town to Turf after the current contractor leaves the site at the end of April.
Full council record
Purpose
The current contractor for the works is due to
leave the site at the end of April. As paving works will require
completion after this date, the Council requires an alternative
contractor to complete the project.
Content
Ridwan Musa, Head of Highway Operations and
Design, took a decision after a competitive exercise, to award a
contract to Holderness Groundworks &
Paving Ltd, 381 Brindle Road, Bamber Bridge,
Preston, PR5 6AP (company number 9822072.).
Details
| Outcome | Recommendations Approved |
| Decision date | 17 Apr 2024 |