Changes to the Bridges Maintenance Capital Programme

March 27, 2025 Director of Highways and Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve the reallocation of £9841.46 from a completed retaining wall project to several other completed bridge maintenance projects to reconcile their finances before the end of the financial year, with no change to the overall approved budget.

Full council record

Purpose

Proposed amendments to the Highways, Bridges Maintenance Capital Programme

Executive Summary.

Head of Service is asked to approve the reallocation of funds within the above programme to allow projects to be closed and financially reconciled ahead of the Financial Year end. The amounts detailed will allow outstanding, unprocessed cost items costs to be settled. Details of the proposed reallocations are as follows:

Transfer a total of £9841.46 from completed project id 14935 24/25 30423 Church Brow Retaining Wall to the following projects to allow them to be reconciled

£1000 to project 12764 22/23 6602 Peel Road

£2000.23 to project 12780 22/23 4661 Yorkshire Street Aqueduct

£300 to project 12779 22/23 1000B Carr Road Canal

£3500 to project 13984 23/24 6188 Worsley Park

£325.31 to project 11454 21/22 Moor Street Railway Bridge

£2715.92 to project 13990 23/24 1072 Grindleton

The reallocations are between completed projects in the same programme and there is no change to the total approved budget.

Background

Budget allocations are regularly reviewed to ensure the programme is delivered within available resources and completed project budgets reconciled.

Consultations

N/A

Risk management

The changes are required to ensure that the budget is managed effectively.

Financial

There is no change to the approved programme budget. This item does not require cabinet approval.

Christopher Wilding

Bridges and Structures Design Manager

27th March 2025.

Decision

John Davies, Head of Highway Network Management, on behalf of the Matt Townsend, Director of Highways and Transport, took a decision to approve changes to the Bridges Maintenance Capital programme detailed in this report.

Supporting Documents

Report.pdf

Details

OutcomeRecommendations Approved
Decision date27 Mar 2025