...to approve the allocation of £2 million from the 26/27 capital highway allocation for the repair of Ramsclough Retaining Wall on B6236 Haslingden Old Road, in order to expedite the project and reopen the road sooner than initially planned.
Full council record
Purpose
Head of Service is asked to approve a decision by Capital Board to allocate funding for the repair of Ramsclough Retaining Wall.
The date of the approval was 15/08/2025
The report was submitted by Paul Binks, Highway Asset Manager.
A landslip occurred along the B6236 Haslingden Old Road following heavy rain at the start of the New Year, which saw a number of flooding incidents across the county. The landslip caused a wall supporting the road and one lane of the carriageway to collapse.
The road has been closed ever since, with temporary diversion routes in place, as it is not safe for vehicles to continue using the remaining carriageway, even under traffic control.
£1m was approved in the 25/26 Capital New Starts Highway Maintenance Programme, approved by Cabinet in March'25, for site clearance and preparatory works.
It was intended to undertake a procurement exercise and for the reinstatement works to start in 26/27 with approval being sought from Cabinet in March'26. Due to the strategic nature of the road, environmental considerations and reputational issue if the road is not reinstated in a timely manner it is proposed to bring forwards the works to January\February 26.
Amount requested from the 26/27 programme £2m.
If this project is overspent, funding will be made available through reconciliation of underspends from completed projects.
If the highway surface is not replaced then we will be in breach of our statutory duties to maintain the highway and would carry on incurring traffic management costs and costs in monitoring a dangerous structure.
Decision
Kirstie Williams, Interim Head of Service, Highways Operations and Design, on behalf of Matt Townsends, Director of Highways and Transport, took the decision to allocate funding for the repair of Ramsclough Retaining Wall.