S278 Cleveleys and Garstang Highway Works Additional Construction Work Funds

October 6, 2025 Director of Highways and Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Director of Highways and Transport approved recommendations on 06/10/2025. Monies up to £721,900 were brought into the Capital Programme to cover design and construction costs for highway works in Cleveleys and Garstang.

Full council record

Purpose

Wyre Council received a grant to improve the amenities on parts of Victoria Road West, Princess Road, Slinger Road, Roughly Road and North Promenade in Cleveleys and Garstang High Street in Garstang.
The highway construction for Princess Road, Slinger Road, Rough Lea Road and North Promenade Cleveleys. works commenced on 17th March and are now complete.
The remaining works on Victoria Road West and Garstang High Street are to be constructed shortly and will be carried out by Highway Operations through a S278 agreement with Wyre Council.
The advance payment of fees and the Section 278 Agreement provides a robust mechanism for the County Council to ensure it is at no financial risk from carrying out the design, construction and supervision of these work.

Decision

Kirstie Williams, Interim Head of Service, Highway Operations and Design, on behalf of the Matt Townsend, Director of Highways and Transport took a decision to bring monies, up to a maximum amount of £721,900 into the Capital Programme to cover the design and construction cost of the Cleveleys and Garstang Highway works.

Supporting Documents

Report.pdf

Details

OutcomeRecommendations Approved
Decision date6 Oct 2025