Changes to the Bridges Maintenance Capital Programme
October 17, 2025 Director of Highways and Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Director of Highways and Transport, acting through Kirstie Williams, Interim Head of Highway Operations and Design, approved changes to the Bridges Maintenance Capital Programme on 17/10/2025. The decision approved the reallocation of £45,000 from the Chadswell Retaining Wall project to the Healey Dell project. This reallocation allows for additional work required to complete the Healey Dell project within the existing total budget.
Full council record
Purpose
Proposed amendments to the Highways, Bridges Maintenance Capital Programme
Executive Summary
As part of the normal process of service delivery, the approved highways capital programme now requires amendments to meet emerging priorities and allow the effective delivery the Programme.
Head of Service is asked to approve the reallocation of funds within the above programme. Details of the proposed reallocation are:
Transfer £45,000 from completed project ID 16419 25/26 Chadswell Retaining Wall 32730 - T1 to project ID 16280 25/26 Healey Dell 30850 - T1.
The reason for the above reallocation is that additional work is required to complete project 16280 because the existing foundation has been extended as it was not wide enough to allow the parapet wall to be constructed and maintain enough width in the carriageway.
The reallocations are between projects in the same programme and there is no change to the total approved budget. The changes will allow the total number of live projects to be reduced, completed projects to be reconciled and available funds released to support delivery of the programme. There are transfers between projects in different programme years. This is to ensure that funds are used effectively by supporting project delivery.
Decision
Kirstie Williams, Interim Head of Service Highway Operations and Design, on behalf of the Matt Townsend, Director of Highways and Transport, took a decision to agree the changes to allow the programme to be delivered effectively within the total budget.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 17 Oct 2025 |