2025/26 Quarter 2 Financial Monitoring Report
November 27, 2025 Cabinet (Cabinet collective) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
... to address a projected £10.354m revenue overspend and a £50.464m capital underspend, they approved the revised 2025/26 Capital Programme of £297.912m as detailed in the report.
Full council record
Purpose
This report provides an update to Cabinet on the Council's 2025/26 revenue and capital financial position, as at the end of Quarter 2. Securing sound and robust finances is the number one priority for the Administration as financial security enables the delivery of the Council's ambition for providing efficient and effective county services to the residents of Lancashire.
The forecast position at the year-end at Quarter 2 is based on several assumptions relating to current expenditure, expected demand, cost pressures and service knowledge and a risk assessment of savings delivery trends and service knowledge.
Lancashire County Council is not unique in facing spending pressures and challenges in delivering council services and demands upon services. Lobbying by the local government sector of government for increased resources continues in advance of the outcome of the Fair Funding Review 2.0 due in the Autumn. Nonetheless, constraining expenditure streams within agreed budget totals is central to the Council’s mission to attain financial control in its operations generally.
The forecast revenue outturn position for 2025/26 at the end of Quarter 2 is an overspend of £10.354m, which represents 0.83% of the approved budget. Services have prepared and continue to develop mitigation strategies with the aim of eliminating or reducing to the maximum extent possible all of these adverse variances. The Quarter 3 position will set out the results of these endeavours and in the meantime the position will be closely monitored.
The 2025/26 Capital Programme agreed by Full Council in February 2025 of £299.635m was the highest value programme agreed in recent years (in financial year 2024/25 Capital Programme delivery of £199.152m was achieved).
The Programme has been revised to take account of the roll forward from the last financial year, additional grants received and a review of the profiling of likely spend at the year-end for those projects that will be delivered over a longer period than expected in February, which is established practice for a programme of this size and complexity. The value of the Revised Programme has therefore been adjusted in the sum of £297.912m. Approval of this Revised Programme is detailed in the recommendations of the report and details by service blocks are shown in Appendix 'B'.
The forecast outturn against the Revised Capital Programme in the current year is £247.448m resulting in a forecast underspend of £50.464m (16.94%). This forecast delivery of £247.448m represents 124% of the delivery achieved in 2024/25. As is usual with the delivery of large and complex programming it is not unlikely that this underspend will increase as the financial year progresses.
Decision
The Cabinet approved the recommendation(s) as set out in the report.
Details
| Outcome | Recommendations Approved |
| Decision date | 27 Nov 2025 |
| Effective from | 3 Dec 2025 |