Reallocate capital underspends to offset projected overspends in the Highway Maintenance Capital delivery programme for 2025/26
January 15, 2026 Director of Highways and Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Director of Highways and Transport approved the reallocation of capital funds on 15/01/2026. The decision approved the reallocation of £7379.80 to cover overspends on Paythorne Bridge Widening and added new projects including Red Bridge, Lancashire Moor Road Drainage, Derby Street Bridge Signage, Cemetery Lodge / Lark Hill Lane Survey, and Clitheroe Trash Screen.
Full council record
Purpose
As part of the normal process of service delivery, the approved highways capital programme now requires amendments to meet emerging priorities and allow the effective delivery of the Programme. Head of Service is asked to approve the reallocation of funds within the above programme. Details of the proposed reallocation are:
1. To balance overspends within the Planned Additional Maintenance programme
a. 23/24 14095 Paythorne Bridge Widening requires £7379.80 to be funded from 14004 23/24 Unallocated -£7379.80
2. To add new projects to be funded from the 25/26 unallocated 16639
a. Red Bridge, Eyes Lane Design £20,000
b. Lancashire Moor Road Drainage £15,000
c. Derby Street Bridge Signage £10,000
d. 4972 Cemetery Lodge / 9661 Lark Hill Lane Survey £25,000
e. Clitheroe Trash Screen £20,000
Decision
John Davies, Head of service for Highways Network Management, on behalf of the Matt Townsend, Director of Highways and Transport, took a decision to approve the reallocation of funds as set out in the report.